Campbellsville Forward and Backward Pass Using AON Project Management Case

Question Description

Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:

Activity

Description

Predecessors

Duration (Days)

A

Site selection

None

4

B

Buy concessions

A

4

C

Rent facilities

A

2

D

Build stands

A

5

E

Generator & wiring installation

C

2

F

Security

B

4

G

Lighting installation

E

2

H

Sound system installation

E, F

2

I

Stage construction

D

3

J

Tear down

G, H, I

4

  1. Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
  2. Identify all paths through the network. Which is the critical path?
  3. Which activities have slack time?
  4. Identify all burst activities and merge activities.