Select Page

Texas A & M University Earned Value Management Case Study

Question Description

Need help in writing the following two question of 100 words each. Please use textbook as main source.

  1. It has been said that Earned Value Management (EVM) came about because the Federal Government often used “Cost-plus” contractors with project organizations. Cost-plus contracting allows the contractor to recover full project development costs plus accumulate profit from these contracts. Why would requiring contractor firms to employ earned value management help the government hold the line against project cost overruns?
  2. What do the Schedule Performance Index and the Cost Performance Index demonstrate? How can a project manager use this information to estimate future project performance?’

Case study should be minimum of 1.5 page. Please use textbook as main source.

Case 13.3 “Dear Mr. President—Please Cancel our Project!”: The Honolulu Elevated Rail Project

This case is a great current example of a very expensive project that was kicked off because of an assumed need—to relieve congestion in downtown Honolulu through an elevated urban rail system. Critics argue that in addition to having a ballooning cost, the actual planning was poorly conceived, leaving Honolulu with an intrusive and ugly rail system through the downtown area, ruining panoramic views, and impeding traffic. Additionally, advocates underestimated the power needs for the rail system, requiring the transport authority to renegotiate electricity fees for the system. Finally, the original costs that were assumed for the project were calculated during an economic downturn and with the economy booming again, the costs of the project have gone up dramatically. All of these elements points to a state Governor who is anxious to be rid of the project and hoping that President Trump will deny additional federal funding, in which case the project will likely be cancelled.

Questions

  1. Why are public works projects like the Honolulu Rail project nearly impossible to stop once they have been approved, even if later cost estimates skyrocket?
  2. Project Management researchers have charged that many large infrastructure projects, like this one, suffer from “delusion” and “deception” on the parts of their advocates. Explain how “delusion” might be a cause of ballooning budgets in this project. How does “deception” affect the final project budget overruns?

"Place your order now for a similar assignment and have exceptional work written by our team of experts, guaranteeing you "A" results."

Order Solution Now